Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Rough Seas Delay Block Island Subsea Cable Installation
Wind Farms

June 7, 2016 · about 10 years ago

Rough Seas Delay Block Island Subsea Cable Installation

Adverse sea conditions have pushed back the installation of the 20-mile National Grid submarine cable from Narragansett, Rhode Island, to Block Island by one week. The cable laying barge Big Max was initially scheduled to install the cable last week, however, rough sea conditions postponed the works

1 minutes read
  • LinkedIn
  • X
  • Email

Adverse sea conditions have pushed back the installation of the 20-mile National Grid submarine cable from Narragansett, Rhode Island, to Block Island by one week.

The cable laying barge Big Max was initially scheduled to install the cable last week, however, rough sea conditions postponed the works and the vessel is expected to start working off the Scarborough Beach later this week.

The subsea cable will export the electricity produced by the first offshore wind farm in US waters, the 30MW Block Island, from Block Island to the mainland.

The Big Max and associated support vessels will be positioned off the shore of Scarborough Beach for a couple of days while the submarine cable is fed through the conduit and into the land/sea transition vault.

Once the cable is secured in the vault, the barge will begin the approximate two week, 20-mile journey to Block Island, burying the cable roughly 4-6 feet below the sea floor.

The Big Max started laying the 8-mile subsea link between the wind farm and Block Island in early May. The works were completed on 27 May.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free