Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Block Island Turbine Out of Action Until Second Half of February
Wind Farms

December 26, 2016 · about 9 years ago

Block Island Turbine Out of Action Until Second Half of February

One of the General Elecetric’s (GE) Haliade turbines installed at America’s first offshore wind farm will be out of action at least until the second half of February, according to a statement issued by Block Island Wind Farm’s Fisheries Liaison, Elizabeth Ann Marchetti. The wind farm’s turbine numbe

1 minutes read
  • LinkedIn
  • X
  • Email

One of the General Elecetric’s (GE) Haliade turbines installed at America’s first offshore wind farm will be out of action at least until the second half of February, according to a statement issued by Block Island Wind Farm’s Fisheries Liaison, Elizabeth Ann Marchetti.

The wind farm’s turbine number two did not go online together with the remaining four 6MW turbines on 12 December, due to a displaced drill bit.

The drill bit was left in the air gap of the turbine’s generator during manufacturing in GE factory in France, according to a statement issued by Marchetti.

As a consequence, the turbine reportedly suffered scratches on 26 of its magnets.

The drill bit has subsequently been removed from the air gap. The generator is in working condition but the damaged magnets now need to be replaced, Marchetti said.

GE will deploy the lift boat Lacie Eymard to provide accommodation for the technicians that will be working on the repairs.

The technicians are expected to start working on the site in early January, weather dependent, and the magnet replacement is scheduled to be completed within 45 days.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsAuthorities & GovernmentOperations & MaintenanceStorageTechnology

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free