Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Siem Installs Veja Mate Inter-Array Cables 10 Weeks Early
Wind Farms

February 6, 2017 · about 9 years ago

Siem Installs Veja Mate Inter-Array Cables 10 Weeks Early

Siem Offshore Contractors has completed the inter-array cable installation and post-lay burial activities at the Veja Mate offshore wind farm in German North Sea ten weeks ahead of schedule. Cable installation started on 1 October, and since then Siem successfully installed 73 composite submarine po

1 minutes read
  • LinkedIn
  • X
  • Email

Siem Offshore Contractors has completed the inter-array cable installation and post-lay burial activities at the Veja Mate offshore wind farm in German North Sea ten weeks ahead of schedule.

Cable installation started on 1 October, and since then Siem successfully installed 73 composite submarine power cables totaling 97 kilometres in length using their Siem Aimery and Siem Moxie vessels for cable laying and installation support.

Termination and testing activities will be completed within the next few weeks.

The inter-array grid will connect the wind farm’s 67 Siemens 6MW turbines with an offshore substation which will collect the electricity generated by the wind turbines and send it to the mainland via export cables.

Veja Mate’s IAC Package Manager Klaus Zwirlein said: “We are happy to have brought this project to a successful end, ahead of schedule. Although the weather was kind to us, our achievement was realized thanks to the great team effort of our IAC staff and SOC project teams for their dedication and commitment.“

Veja Mate is a 402MW, EUR 1.9 billion offshore wind project owned by the Highland Group Holdings Ltd, Siemens Financial Services and CI II managed by Copenhagen Infrastructure Partners.

Bank financing for the project was completed on 1 July 2015. Construction started on 4 April 2016 and the project is expected to be fully operational by the end of 2017.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsStorage

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free