Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›North Myrtle Beach Renourishment Set for September
Dredging

July 6, 2017 · about 9 years ago

North Myrtle Beach Renourishment Set for September

A $10.6 million emergency U.S. Army Corps of Engineers beach renourishment project is scheduled to begin during the September/October 2017 time frame in the city of North Myrtle Beach, SC. The city of North Myrtle Beach will not have to pay for the emergency project, according to the city’s latest a

2 minutes read
  • LinkedIn
  • X
  • Email

A $10.6 million emergency U.S. Army Corps of Engineers beach renourishment project is scheduled to begin during the September/October 2017 time frame in the city of North Myrtle Beach, SC.

The city of North Myrtle Beach will not have to pay for the emergency project, according to the city’s latest announcement.

Around 400,000 cubic yards of material will be placed on areas of the beach that do not have adequate dune protection.

Once the emergency beach renourishment project has concluded, the city of North Myrtle Beach will contract to have about 50,000 cubic yards of sand delivered to create dunes that were eliminated or severely eroded during Hurricane Matthew.

The city is currently in the permitting phase of this dune replacement project.

“We are very grateful that this emergency beach renourishment project will soon bring much needed sand to sections of our beach that were severely eroded during Hurricane Matthew,” said North Myrtle Beach Mayor, Marilyn Hatley.

“We have so many people to thank, including the U.S. Army Corps of Engineers, our City Council, our federal and state legislative delegations, our city staff, and others, who came together to work to bring this $10.6 million emergency project to fruition at no cost to the city.”

The North Myrtle Beach project is part of the larger Myrtle Beach Storm Damage Reduction Project.

The U.S. Army Corps of Engineers, Charleston District, recently awarded a $26.3 million contract for the Myrtle Beach Storm Damage Reduction Project to Great Lakes Dredge and Dock Company, LLC, which will place a total of about 1.2 million cubic yards of material on North Myrtle Beach and Garden City and Surfside Beaches.

This overall project is funded through federal emergency beach rehabilitation funding from Hurricane Matthew, along with cost-shared construction funding appropriated through Congress.

The construction will begin near Surfside Beach Pier no earlier than July 15th and continue north toward Myrtle Beach State Park. This will take about 25-35 days, barring any significant weather or mechanical delays.

After that section is complete, renourishment will move south from the Surfside Beach Pier toward the southern project boundary in Georgetown County. This section will take an additional 30-35 days and should be complete by mid-September.

The Corps will be placing approximately 800,000 cubic yards of material on approximately 7.5 miles of Garden City and Surfside Beaches.

The project will then move to the city of North Myrtle Beach.

[mappress mapid=”24252″]

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free