Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Prosafe stalls delivery of two newbuild accommodation rigs
Fossil Energy

December 7, 2017 · about 8 years ago

Prosafe stalls delivery of two newbuild accommodation rigs

Prosafe has further extended its standstill agreement with China’s Cosco Qidong shipyard for two semi-submersible accommodation rigs.

2 minutes read
  • LinkedIn
  • X
  • Email

Offshore accommodation specialist Prosafe has further extended its standstill agreement with China’s Cosco Qidong shipyard for two semi-submersible accommodation rigs, Safe Nova and Safe Vega.

In addition, the flotel owner is keeping its newbuild unit Safe Eurus in a preserved, strategic stacking mode at the shipyard while negotiations continue with Cosco to find a workable commercial solution.

Prosafe said on Thursday it continues to work with Cosco to find a commercial solution for the three units that currently reside in shipyard in China.

According to the company, the standstill agreement related to Safe Nova and Safe Vega has recently been extended until April 20, 2018. The previous standstill agreement expired in December.

Executing its plans on fleet renewal, Prosafe bought these two accommodation rigs from Axis Offshore late last year while they were still being built by the Chinese shipyard. At the same time, the delivery of Prosafe’s Safe Eurus unit was also pending. Namely, Prosafe in July 2016 agreed with Cosco to postpone the delivery of the Safe Eurus to 4Q 2019 amid refinancing efforts.

Prosafe reiterated it remains in negotiations with COSCO and related parties for a workable commercial solution for Safe Nova and Safe Vega. If no agreement is reached, Prosafe stated it has the right to claim cancellation of the newbuild contracts due to delay, and claim repayment of the installments paid including interest of about $60 million in total, secured by a refund guarantee from Bank of China.

Offshore Energy Today Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyExploration & Production

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free