Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Brevard County Beach Works About to Begin
Dredging

December 12, 2017 · about 8 years ago

Brevard County Beach Works About to Begin

Port Canaveral was the site for a conference that outlined plans to renourish Brevard County beaches as part of the Brevard County Shore Protection Project. The pre-construction meeting was organized by the U.S. Army Corps of Engineers as the lead coordinator to provide details of the $17.4 million

2 minutes read
  • LinkedIn
  • X
  • Email

Port Canaveral was the site for a conference that outlined plans to renourish Brevard County beaches as part of the Brevard County Shore Protection Project.

The pre-construction meeting was organized by the U.S. Army Corps of Engineers as the lead coordinator to provide details of the $17.4 million dollar project, which is expected to get underway in late January, 2018.

The Corps awarded the contract to Great Lakes Dredge and Dock Company of Oak Brook, IL to remove 1.172 million cubic yards from the Bureau of Ocean Energy Management (BOEM) regulated offshore Canaveral Shoals II Borrow area.

A total of 825,000 cubic yards will be placed in the North Reach area, which consists of beaches in North Cocoa Beach, and Cape Canaveral. The remaining 397,000 cubic yards will be placed in the South Reach area, which includes beaches in Indialantic and Melbourne Beach.

Beaches in Brevard County are routinely scheduled for full renourishment every 5-6 years, with the last project completed in 2014. Hurricane Matthew in 2016 and Hurricane Irma this year made it necessary for an expedited replenishment schedule for the South Reach, which was organized by the U.S. Army Corps of Engineers in coordination with Brevard County.

Liz Fiocchi, Project Manager and Navigation Business Line Manager for the Jacksonville District said that plans are in place to get the project underway in late January 2018. “ This renourishment is to replace what was taken by the recent storms with the next full beach renourishment planned for 2021 or 2022.”

In addition to Port Canaveral staff and the Army Corps representatives, other officials participating in the conference included the Bureau of Ocean Energy Management (BOEM), U.S. Fish and Wildlife Service, Florida Department of Environmental Protection (DEP), Florida Fish and Wildlife Conservation Commission, Canaveral Pilots Association, Brevard County, City of Cocoa Beach, Melbourne Beach, Indialantic and Cape Canaveral.

The project is estimated to be completed by April 30, 2018, prior to the commencement of turtle nesting season.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free