Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›White Point Swash Project on the Table
Dredging

January 24, 2018 · about 8 years ago

White Point Swash Project on the Table

Horry County, the Town of Briarcliffe Acres, and the City of North Myrtle Beach have been involved in a lengthy period of pre-application consultation with the Army Corps regarding a desire to realign the outlet of White Point Swash and to dredge material blocking water flow in the basin. Recent hur

2 minutes read
  • LinkedIn
  • X
  • Email

Horry County, the Town of Briarcliffe Acres, and the City of North Myrtle Beach have been involved in a lengthy period of pre-application consultation with the Army Corps regarding a desire to realign the outlet of White Point Swash and to dredge material blocking water flow in the basin.

Recent hurricanes and other storms affected the swash outlet and the basin.

According to the City of North Myrtle Beach, the jurisdictions have been informed that they must submit a full individual wetland permit application for the proposed project.

Horry County’s wetland permitting consultant has submitted the application to the U.S. Army Corps of Engineers on behalf of the Town of Briarcliffe Acres (the lead applicant) for the proposed work.

The application will now go through a joint federal-state review process, which will take at least six months. The process could take longer if any commenting agencies have significant concerns about the proposed project.

“ At the very least, an approved permit would come with conditions limiting or prohibiting construction during sea turtle nesting season May through October ,” the City of North Myrtle Beach said.

The city added that if a permit is given, it would be a 10-year federal permit and a 5-year renewable state permit so that future realignment work occurs through notification, instead of another permit approval process.

The officials are hopeful permit approval would occur in the late summer or early fall of 2018, allowing work to occur during winter 2018-2019. The Town of Briarcliffe Acres, Horry County and the City of North Myrtle Beach would pay for the work.

[mappress mapid=”24795″]

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free