Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Big Milestone for Tangier Island Jetty Project
Dredging

September 26, 2018 · about 8 years ago

Big Milestone for Tangier Island Jetty Project

Governor Ralph Northam this week announced completion of a project partnership agreement between the U.S. Army Corps of Engineers and the Virginia Marine Resources Commission (VMRC) to launch the design and construction of the Tangier Island Jetty in Accomack County. This federal and state funded in

2 minutes read
  • LinkedIn
  • X
  • Email

Governor Ralph Northam this week announced completion of a project partnership agreement between the U.S. Army Corps of Engineers and the Virginia Marine Resources Commission (VMRC) to launch the design and construction of the Tangier Island Jetty in Accomack County.

This federal and state funded infrastructure project will protect the western portion of the navigation channel and harbor for the Town of Tangier and the associated seafood industry infrastructure.

The Tangier Island Jetty involves construction of a straight stone jetty at the southwestern tip of Uppards Island, extending south into the water approximately 494 feet from its point of origin into the navigation channel.

“ The jetty project will help protect the Town’s navigation channel and harbor from wave action and adverse weather conditions than can damage work boats, docks, and crab houses ,” said VMRC Commissioner Steven G. Bowman .

In 1994, Congress authorized the U.S. Army Corps of Engineers to study a jetty for the Town of Tangier to protect the navigation channel and infrastructure along it. The initial phase of this project was launched in 1995 with a reconnaissance report.

A full feasibility study was initiated in 2009. In the feasibility study, USACE considered several measures to protect the navigation channel from wave action. The study included a revetment, a jetty, offshore breakwaters, geotextile tubes, and relocating harbor facilities.

Ultimately, the only measure that was deemed to be effective and feasible was the construction of a jetty. Costs for design and construction of the Tangier Island Jetty project total $2,646,000, with 20 percent provided through state funding.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free