Norway OKs Lundin’s plan for first Edvard Grieg tie-back

Lundin Petroleum has received final approval for the plan for development and operation for the Solveig field from the Norwegian Ministry of Petroleum and Energy.

2 minutes read
  • LinkedIn
  • X
  • Email

Oil and gas company Lundin Petroleum has received final approval for the plan for development and operation (PDO) for the Solveig field from the Norwegian Ministry of Petroleum and Energy.

Lundin filed the plan for the development of the Solveig field – previously called Luno II – in late March 2019.

The Solveig field is the first tie-back development project to the Lundin Norway-operated Edvard Grieg platform on the Utsira High, Norway.

Lundin said on Wednesday that first oil from Solveig phase 1 in PL359 is expected in the first quarter of 2021 with a forecast gross peak production of 30 Mboepd.

Phase 1 capital cost is estimated at $810 million gross ($527 million net to Lundin), with a breakeven below $30 per boe and consists of three horizontal oil production wells and two water injection wells.

The contract for the modification of the Edvard Grieg field facilities has been awarded to Rosenberg WorleyParsons and the subsea system contract has been awarded to TechnipFMC under a lump sum engineering, procurement, construction, and installation contract (EPCI).

Drilling work will be undertaken using the West Bollsta high specification semi-submersible rig, which is operated by Seadrill.

Lundin is the operator of Solveig with a 65 percent working interest and the partners are OMV and Wintershall DEA with 20 and 15 percent working interest respectively, the same as Edvard Grieg.

Alex Schneiter , CEO and President of Lundin Petroleum, commented: “I am very pleased to note the final approval from the Ministry of Petroleum and Energy for the PDO of Solveig; this is our first tie-back project to Edvard Grieg and is an important part of the future for the Greater Edvard Grieg Area solution. We have assembled a very good team to lead the project, supported by industry leading contractors and I look forward to reporting on its progress as we head towards first oil in early 2021.”

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Project & Tenders

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Jan De Nul makes its entrance into CCS market with North Sea pipeline project
  2. 2Floatel’s 2016-built semi-submersible vessel lines up Brazilian job
  3. 3PTTEP, Petronas’ 35-year gas deals bolster Thailand-Malaysia energy security axis
  4. 4Well-Safe and NMC Energy join forces for North Sea decommissioning push

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free