Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid›Kriegers Flak CGS launch delayed again
Grid

July 3, 2020 · about 6 years ago

Kriegers Flak CGS launch delayed again

The launch of Kriegers Flak Combined Grid Solution (CGS) has again been delayed, now until the end of September. The final steps of the commissioning procedures for the overall CGS system are confronted with ongoing movement restrictions for the Swedish team members due to the coronavirus pandemic,

1 minutes read
  • LinkedIn
  • X
  • Email
Kriegers Flak CGS launch delayed again
Energinet

The launch of Kriegers Flak Combined Grid Solution (CGS) has again been delayed, now until the end of September.

The final steps of the commissioning procedures for the overall CGS system are confronted with ongoing movement restrictions for the Swedish team members due to the coronavirus pandemic, according to Energinet.

“50Hertz and Energinet are monitoring the situation very closely and are making all efforts to further use alternative ways to continue the individual commissioning steps and make it possible for team members to work on site,” the company wrote.

The commissioning of the 400 MW offshore grid link was originally planned for the end of 2018, and was for the first time delayed for the first quarter of last year. In October 2018, Energinet informed that the launch date was pushed back to May 2019.

Last year, the interconnection was again rescheduled, to the fourth quarter of 2019.

At the beginning of this March, Energinet reported a postponement by a few months, with the then expected launch time being in the second quarter of this year. The launch was then delayed until the end of August.

Two offshore cables of the CGS were installed in July 2018, connecting the platform of Denmark’s 605 MW Kriegers Flak offshore wind farm with the platform at the German 288 MW Baltic 2 offshore wind farm, operational since 2015.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

GridOffshore WindBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free