Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›East Anglia One offshore wind farm completes final commissioning
Offshore Wind

July 28, 2020 · about 6 years ago

East Anglia One offshore wind farm completes final commissioning

The 714 MW East Anglia One offshore wind farm has completed the final commissioning, with all 102 Siemens Gamesa 7 MW turbines now operational. Around 20% of the turbine installation and around half the turbine connection work was completed during the lockdown, ScottishPower Renewables said. Accordi

1 minutes read
  • LinkedIn
  • X
  • Email
East Anglia One offshore wind farm completes final commissioning
ScottishPower – EAONE Sun Haze

The 714 MW East Anglia One offshore wind farm has completed the final commissioning, with all 102 Siemens Gamesa 7 MW turbines now operational.

Around 20% of the turbine installation and around half the turbine connection work was completed during the lockdown, ScottishPower Renewables said.

According to the company, this included a number of changes in daily work, such as switching to a higher number of smaller vessels, creating crew households who lived and worked together at all times, introducing new welfare protocols and minimizing crew changes.

“The final commissioning of East Anglia ONE is an incredible milestone for us and our project partners, as well as our wider stakeholders, the East Anglian region and the whole of the UK. And it comes at a crucial time as the UK takes it first steps towards a green economic recovery,” said Charlie Jordan , East Anglia ONE Project Director at ScottishPower Renewables.

The first of the 102 turbines began generating power and delivering it to the onshore substation at Burstall, near Bramford, in September 2019. This April, the final unit was installed .

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free