Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Foundations›Jan De Nul and Hitachi shift into overdrive offshore Taiwan
Foundations

August 13, 2020 · about 6 years ago

Jan De Nul and Hitachi shift into overdrive offshore Taiwan

Jan De Nul has installed nine of the 21 jacket foundations at the Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration offshore Taiwan. Offshore installation vessel Aegir, which Jan De Nul Group chartered from Dutch Heerema Marine Contractors, is installing the 1,100 metric tonne j

1 minutes read
  • LinkedIn
  • X
  • Email
Jan De Nul and Hitachi shift into overdrive offshore Taiwan
Jan De Nul

Jan De Nul has installed nine of the 21 jacket foundations at the Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration offshore Taiwan.

Offshore installation vessel Aegir, which Jan De Nul Group chartered from Dutch Heerema Marine Contractors, is installing the 1,100 metric tonne jackets at the site some ten kilometres off the coast of Fangyuan in Changhua County.

Turbine Installation to Start in August

In total, the 109.2 MW TPC Changhua offshore wind farm Phase 1 will comprise 21 Hitachi 5.2 MW offshore wind turbines.

Jan De Nul’s consortium partner Hitachi Ltd. continues to mobilize the turbine components to the marshalling port of Taichung, to allow preparation for offshore installation in August with Jan De Nul’s offshore jack-up installation vessel Taillevent .

Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the 21 typhoon-certified offshore wind turbines using a downwind rotor.

The Jan De Nul–Hitachi consortium is also responsible for the first five years operation and maintenance (O&M) of the TPC Changhua offshore wind farm Phase 1.

Onshore Work Completed

Jan De Nul has now completed all onshore civil works needed for the connection of the offshore wind farm to the Taiwanese power grid.

For the connection of the subsea cable at the landfall with the onshore substation of Changhua County, Jan De Nul Group constructed 13 kilometres of duct banks in collaboration with the Taiwanese company Star Energy Corporation.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FoundationsGridOffshore WindTurbinesVesselsWind FarmsPorts & Logistics

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free