Home›Clean Fuel›Sleipnir SSCV installs Tolmount platform in North Sea
Clean Fuel

October 15, 2020 · about 5 years ago

Sleipnir SSCV installs Tolmount platform in North Sea

Heerema’s Sleipnir, the LNG-powered world’s largest semi-submersible crane vessel, has installed the Tolmount platform In the Southern North Sea.

2 minutes read
  • LinkedIn
  • X
  • Email
Sleipnir lifting Tolmount jacket; Source: Rosetti Marino
Sleipnir lifting Tolmount jacket; Source: Rosetti Marino

Heerema’s Sleipnir, the LNG-powered world’s largest semi-submersible crane vessel, has installed the Tolmount platform In the Southern North Sea.

Heerema said on Thursday that the project consisted of installing the 2,350 metric ton jacket and 2,500 metric ton topside constructed by Rosetti Marino.

Sleipnir arrived Tolmount field, located 40 kilometres off the coast of the UK in a water depth of around 51 metres, on October 7.

Installation began on October 12 when the jacket was safely lifted from the Heerema barge H-408. After finalizing jacket and pile installation, Sleipnir lifted and installed the 2,500 metric ton topside on October 13.

The Tolmount jacket and topside arrived at the Tolmount field following a 5,390-kilometre journey from Rosetti’s yard in Ravenna, Italy.

The platform will be a normally unattended installation, located in the vicinity of the 42/28d-13 appraisal well, and will handle wet gas production from four platform wells. The Premier Oil-operated Tolmount field development is on track to deliver first gas in the second quarter of 2021.

Rosetti Marino managed the construction and installation of the low-carbon design jacket and topside on behalf of client Premier Oil. The project involved more than 1,100,000 manhours and was completed over a duration of 26 months. It is worth reminding that platform construction for the Tolmount platform began in December 2018 .

Michel Hendriks , Heerema transport and installation director, said: “ The close collaboration with Rosetti Marino has been a highlight of the Tolmount project. Despite challenges introduced by the ongoing pandemic, we worked together to find creative solutions, which were handled with total professionalism and high regard for safety “.

In a social media update on Thursday, Rosetti Marino said that phase two of the project will begin soon and will see the company engaged in hook-up activities until the first quarter of 2021.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelFossil EnergyOil & GasBusiness Developments & ProjectsHeavy liftingInfrastructureProject & TendersVessels

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norwegian PSV to continue current charter for additional 100 days
  2. 2Italy’s NextGeo to open office in Germany
  3. 3TotalEnergies finds more oil off Angola, enters two exploration blocks
  4. 4Odfjell Drilling’s new rig busy until 2031 thanks to deal with Vår Energi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free