Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Following restart, IOG working to double North Sea gas project output
Fossil Energy

June 1, 2022 · about 4 years ago

Following restart, IOG working to double North Sea gas project output

IOG is looking forward to doubling the output at its North Sea gas project, after restoring the production following modifications.

2 minutes read
  • LinkedIn
  • X
  • Email
UK player anticipates ‘phased build-up to double’ output at North Sea gas project after bringing it back online
Blythe platform; Source: IOG

UK-headquartered IOG plc is looking forward to a phased increase to double the output at its Saturn Banks Project – Phase 1, located in the UK sector of the North Sea, after restoring the production following modifications to the terminal operated by Perenco (UK) Limited (PUK).

Last week, IOG revealed that the production at the Saturn Banks gas project was shut in following liquids handling issues discovered by Perenco, explaining that a drainage system deficiency was found in two recycle compressors in the Perenco Bacton terminal’s Condensate Stabilisation Unit (CSU).

Related Articles

Fossil Energy

UK player frustrated by production shut-in at North Sea gas project

3 min read

In an update on Wednesday, IOG confirmed that following a PUK modification to one of the CSU’s compressors, the production at the Saturn Banks gas project was duly restored at an initial level of approximately 30 mmscf/d on 31 May 2022.

The company also reaffirmed that the modification of the second compressor was expected to take approximately one more week to enable the production from the project to be gradually restored to its prior stabilised levels of 55-65 mmscf/d over the following weeks.

In addition, IOG emphasises that this is expected to be a gradual process to manage the high levels of liquids currently being worked through the Saturn Banks Pipeline System.

Andrew Hockey , CEO of IOG, commented: “IOG, Perenco and ODE Asset Management have collaborated well to facilitate rapid execution of the PUK terminal modification and allow our production to be resumed at 30 mmscf/d. We look forward to a phased build-up to double that level as fast as technically feasible over the coming weeks.”

The IOG-operated Saturn Banks Project – Phase 1 , which was sanctioned in October 2019, consists of Blythe , Elgood , and Southwark fields in the UK Southern North Sea. The first two fields – Blythe and Elgood – were brought on stream in mid-March 2022. IOG holds a 50 per cent stake in this project and its partner CalEnergy Resources holds the remaining 50 per cent.

The normally unmanned Blythe platform , connected to Saturn Banks Pipeline System that feeds into the associated Saturn Banks Reception Facilities at the Bacton terminal, is used for Blythe and Elgood production.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasBusiness & FinanceBusiness Developments & ProjectsExploration & ProductionOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Technip Energies picks up assignment on Mexican LNG project
  2. 2Expansion move puts US LNG project on path for almost twofold capacity boost
  3. 3Petrobras widens its African offshore portfolio with multiple blocks in Côte d’Ivoire
  4. 4WATCH: Island Offshore’s second ocean energy construction vessel goes to Norway for completion

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free