Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo
Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Pre-emptive repair done to faulty Gwynt y Môr export cable
Cabling

September 6, 2022 · about 4 years ago

Pre-emptive repair done to faulty Gwynt y Môr export cable

N-Sea has completed a pre-emptive repair to one export cable at the Gwynt y Môr offshore wind farm in North Wales. The pre-emptive repair was the second stage of a repair to SSEC3 that saw circa 7.5 kilometers of submarine cable replaced and the circuit returned to full availability. Multi-purpose p

1 minutes read
  • LinkedIn
  • X
  • Email
Pre-emptive repair done at faulty Gwynt y Môr export cable
N-Sea

N-Sea has completed a pre-emptive repair to one export cable at the Gwynt y Môr offshore wind farm in North Wales.

The pre-emptive repair was the second stage of a repair to SSEC3 that saw circa 7.5 kilometers of submarine cable replaced and the circuit returned to full availability.

Multi-purpose pontoon Neptune NP459 carried out the work.

“We are very proud that we achieved this great milestone. We would like to thank our client and the entire team involved in this great team effort to complete the project in a prudent, efficient and safe way,” said Rick van Bruggen , commercial director for subsea cables at N-Sea.

Related Articles

Deepwater Installation

N-Sea sends off pontoon for Gwynt y Môr cable repair project

2 min read

Gwynt Y Mor, located some 13 kilometers off the coast of North Wales, was put into operation in 2015. That same year the project encountered its first issues with the export cable, which then underwent repair .

Five years later, an O&M contractor performing a routine test of the fibers in the spare fiber optic cable (FOC) discovered that all fibers within the spare FOC within subsea export cable 3 (SSEC3) had failed. This initial FOC break was located close to the location where the repair was undertaken in 2015.

Last year, Sumitomo Electric Industries reported that it had won a contract to supply the export cable for the 576 MW offshore wind farm.

Follow Offshore Energy’s Subsea on social media:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingGridOffshore WindSubseaSurveys & InterventionsWind FarmsInfrastructureOperations & Maintenance

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1SED Energy Holdings and Ventura Offshore to unite into one
  2. 2New Boskalis rock installation vessel starts work offshore Poland
  3. 321 companies apply for Norway’s new oil & gas exploration areas
  4. 4Spanish shipyard launches its largest-ever vessel, built for Østensjø Rederi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free