Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Potential delay on the cards for completion of drilling ops at UK North Sea well
Fossil Energy

April 18, 2023 · about 3 years ago

Potential delay on the cards for completion of drilling ops at UK North Sea well

IOG plc has encountered a challenge that could extend its previous drilling duration timeline for the second Blythe production well.

2 minutes read
  • LinkedIn
  • X
  • Email
Shelf Drilling’s Shelf Perseverance jack-up rig; Source: IOG
Shelf Drilling’s Shelf Perseverance jack-up rig; Source: IOG

UK-headquartered IOG plc has encountered a challenge that could extend its previous drilling duration timeline for the second Blythe production well, which is part of the Saturn Banks Project – Phase 1 in the UK Southern North Sea.

The Blythe H2 well was spudded on Sunday, 5 March 2023 with Shelf Drilling’s Shelf Perseverance (former Noble Hans Deul ) jack-up drilling rig, which is under contract with IOG, thanks to a deal signed in 2020 while the rig was still part of Noble’s fleet. Petrofac is the designated well operator. As explained at the time, IOG expected the H2 well to take approximately three months to drill, complete and hook-up, subject to the usual offshore operational risks to scheduling.

Related Articles

Fossil Energy

Shelf Drilling rig spins the drill bit at UK North Sea well

2 min read

In an update on Tuesday, 18 April 2023, IOG outlined that the H2 well was drilled to the Basal Zechstein sequence, however, while drilling through the Hauptdolomit formation within the Zechstein, “an abnormally pressured gas and oil influx” was encountered, with associated drilling fluid losses. The company claims that the risk of such a well control challenge was identified during planning and is being safely managed by Petrofac and Shelf, in collaboration with the IOG team.

Rupert Newall , CEO of IOG, commented: “Encountering a gas and oil influx while drilling through the overburden above the reservoir is a known risk in the Southern North Sea. Associated drilling fluid losses present an additional challenge, however, this is being actively and safely managed by Petrofac, the well operator, and Shelf, the drilling contractor, working closely with the IOG team, to ensure that drilling ahead can be safely resumed.”

However, the firm highlights that this challenge is likely to impact the expected well duration, potentially by up to four weeks, while the associated cost impact will depend largely on the speed of resolution. According to IOG, the influx from the Hauptdolomit has been determined to contain non-commercial quantities of oil and gas and is not related to the target Rotliegendes gas reservoir which is over 500 ft deeper and isolated from the Hauptdolomit.

The well has been displaced to a mud weight above the formation pressure and the UK player underlines that options to progress include isolation of the influx zone with cement and, if necessary, side tracking of the well.

The IOG-operated Saturn Banks Project – Phase 1 – sanctioned in October 2019 – covers Blythe , Elgood , and Southwark fields in the UK Southern North Sea. The first two fields – Blythe and Elgood – were brought on stream in mid-March 2022. IOG holds a 50 per cent stake in this project and its partner, CalEnergy Resources, holds the remaining 50 per cent.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyOil & GasRigsBusiness & FinanceBusiness Developments & ProjectsExploration & ProductionProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Expro lines up 14-well Canadian offshore life-extension campaign
  2. 2TotalEnergies greenlights gas project to feed one-third of Nigeria LNG train expansion
  3. 3Construction ramps up at Orkney Islands’ first link to UK mainland
  4. 4Perenco on offshore platform electrification quest to power Brazil’s shallow-water fields from shore

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free