Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›‘Major milestone’ for UK-Germany subsea link as first cabling stage wraps up (Video)
Cabling

November 28, 2024 · about 1 year ago

‘Major milestone’ for UK-Germany subsea link as first cabling stage wraps up (Video)

Italy-headquartered cable systems giant Prysmian has completed the €2.8 billion NeuConnect interconnector project’s first phase of cabling works in the UK waters, marking an important step in establishing the first direct energy link between the UK and Germany. With converter stations under construc

2 minutes read
  • LinkedIn
  • X
  • Email
The €2.8 billion NeuConnect interconnector project has completed the first phase of cabling works in the UK waters, marking a step in establishing the first direct energy link between the UK and Germa
Source: NeuConnect

Italy-headquartered cable systems giant Prysmian has completed the €2.8 billion NeuConnect interconnector project’s first phase of cabling works in the UK waters, marking an important step in establishing the first direct energy link between the UK and Germany.

With converter stations under construction on the Isle of Grain in Kent and Wilhelmshaven in northern Germany, the 725-kilometer land and subsea cable system is said to create an “invisible energy highway” capable of transferring 1.4 GW of electricity enough to power 1.5 million homes, in either direction.

Led by global investors Meridiam, Allianz Capital Partners, Kansai Electric Power, and TEPCO, the interconnector aims to enhance energy security and integrate renewable energy across both nations.

The first phase of cabling works saw 56 kilometers of onshore and subsea cables installed. Prysmian’s Cable Enterprise vessel has been laying subsea cables in UK waters, burying them beneath the seabed to minimize environmental impacts. Additionally, this phase included ‘pull-in’ works, through new underground ducts to NeuConnect’s Isle of Grain site.

“Completing this first phase of cabling is a major milestone for NeuConnect and an important symbolic moment for the UK and Germany as a major new energy link between both countries begins to take shape,” said Julia Prescot , Chair of NeuConnect.

“As one of the world’s longest interconnectors, this phase of works is very much a first stage in a much longer 725km cabling marathon – we are pleased to have reached this important milestone but are not complacent about the scale of works to be completed, and close working with our industry partners will be crucial in keeping this vital new energy link firmly on track.”

Start of cabling, autumn 2024

NeuConnect began major construction in 2023, as it was granted all key regulatory approvals at the end of the same year, following the second partial approval for the construction and operation of the converter station on the German side.

However, the project commenced major construction in the UK in the summer of 2023 . It was reported at the beginning of November 2023 that the first phase of the construction had been completed .

Foundation works for the UK converter station are ongoing, with piling works also initiated at the German converter station . The cabling installation will pause during the winter and ramp up again in 2025, continuing through UK, Dutch, and German waters until 2027.

Once completed in 2028, NeuConnect will utilize 525 kV high voltage direct current (HVDC) cables, a technology designed to deliver a reliable and efficient connection between the UK and German energy grids.

In August 2024, the C-Horizon vessel was deployed to begin shallow water debris removal, boulder relocation, and pre-lay grapnel run activities in UK waters, clearing the cable route for the first UK-Germany energy link.

Related Articles

Cabling

Pre-lay operations about to begin for first UK-Germany energy link

1 min read

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaVessels & VehiclesBusiness & FinanceBusiness Developments & ProjectsProject & TendersTechnologyVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Petrobras locks in 20-year US supply from Sempra’s LNG project in Lone Star State
  2. 2Hanwha Ocean’s design solution allowing LNG carrier’s switch to ammonia gets ABS’ thumbs-up
  3. 3Exmar’s FLNG conversion earns Bureau Veritas’ seal of approval
  4. 4Denmark opens EU’s first full-scale CO2 storage site

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free