Offshore Energy
  • news
  • test
JobsNewsletter
Offshore Energy logo
Topics
  • News
  • Contracts & Tenders
  • Authorities & Government
  • Automation
  • Business & Finance
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Prysmian’s Monna Lisa picks up its first cable for largest US offshore wind farm-to-be
Business & Finance

April 21, 2025 · about 1 year ago

Prysmian’s Monna Lisa picks up its first cable for largest US offshore wind farm-to-be

Prysmian’s new cable laying vessel (CLV) Monna Lisa has been loaded for the first time with submarine cable, destined for what will become the largest U.S. offshore wind farm once operational. Prysmian reported two days ago that submarine cable for Dominion Energy’s Coastal Virginia Offshore Wind (C

2 minutes read
  • LinkedIn
  • X
  • Email
Prysmian’s Monna Lisa picks up its first cable for what will be US largest offshore wind farm

Prysmian’s new cable laying vessel (CLV) Monna Lisa has been loaded for the first time with submarine cable, destined for what will become the largest U.S. offshore wind farm once operational.

Prysmian reported two days ago that submarine cable for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project was being loaded on Monna Lisa at the Arco Felice plant in Italy.

The keel-laying ceremony for Monna Lisa, a sister vessel to Leonardo da Vinci, was held in Tulcea, Romania, in April 2023 to mark the start of construction, which took around 24 months. VARD launched the 171-meter vessel at the beginning of June 2024, after completing steel cutting, keel laying, generator installation, and hull erection .

The CLV then began its journey of 4,000 nautical miles from Romania to Norway, towed down the Danube River, across the Mediterranean Sea, and up the coast of Portugal and Spain to VARD’s shipyard in Søvik to undertake final fit-out and trials.

Prysmian reported on February 6 that the vessel had joined its fleet .

To remind, Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant (BoP) contractors for the transportation and installation of the foundations and the substations and the engineering, procurement, construction, and installation (EPCI) services for the inter-array and export cables for the CVOW project.

Prysmian is providing three three-core 220 kV HVAC export cables measuring approximately 62 kilometers each, with XLPE insulation and single-wire armouring, for a total of approximately 560 kilometers, while DEME is in charge of overseeing the complete offshore installation works for the foundations, substations, infield cables, and part of the export cables.

DEME laid the first export cable using its cable installation vessel Living Stone in September 2024.

The 2.6 GW CVOW project will feature 176 Siemens Gamesa 14 MW wind turbines and will become the biggest U.S. offshore wind farm once in operation.

In February, Dominion Energy revealed that the wind farm was approximately 50% complete and remains on track for on-time completion at the end of 2026.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Business & FinanceBusiness Developments & ProjectsInfrastructureProject & TendersVessels

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ADES jack-up rig pair lines up drilling jobs in Nigerian and UK waters
  2. 2Odfjell Drilling’s rig remaining with Norwegian oil & gas operator for another year
  3. 3Karoon boosts Brazilian field’s oil output with all wells now online
  4. 4TotalEnergies offloading Mexican shallow water block to Grupo Carso

Related articles

FPSO Cidade de Itajaí; Source: Altera Infrastructure
Business & Finance

Karoon boosts Brazilian field’s oil output with all wells now online

12 days ago

Illustration; Source: TotalEnergies
Business & Finance

TotalEnergies offloading Mexican shallow water block to Grupo Carso

12 days ago

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

FPSO Cidade de Itajaí; Source: Altera Infrastructure
Business & Finance

Karoon boosts Brazilian field’s oil output with all wells now online

12 days ago
Illustration; Source: TotalEnergies
Business & Finance

TotalEnergies offloading Mexican shallow water block to Grupo Carso

12 days ago