Home›Cabling›NKT installs power cables at TenneT’s BorWin5 offshore grid connection
Cabling

August 28, 2025 · about 1 year ago

NKT installs power cables at TenneT’s BorWin5 offshore grid connection

Denmark’s NKT has finalized the installation of a 320 kV high-voltage DC (HVDC) power cable system at the 900 MW BorWin5 offshore grid connection in Germany. The pull-in work to the offshore platform was carried out by the company’s NKT Victoria vessel. NKT was responsible for the delivery and insta

1 minutes read
  • LinkedIn
  • X
  • Email
NKT BorWin5
Source: NKT via LinkedIn

Denmark’s NKT has finalized the installation of a 320 kV high-voltage DC (HVDC) power cable system at the 900 MW BorWin5 offshore grid connection in Germany.

The pull-in work to the offshore platform was carried out by the company’s NKT Victoria vessel.

NKT was responsible for the delivery and installation of 230 kilometers of 320 kV HVDC power cables under a contract signed with the Dutch/German offshore transmission system operator (TSO) TenneT in 2020.

The 900 MW BorWin5 offshore grid connection has a total length of 230 kilometers. The starting point is the converter platform BorWin epsilon, which was installed by Allseas in the German North Sea in May 2025.

Related Articles

Cabling

NKT to provide power cable system for BorWin5 offshore wind connection

1 min read

There, the three-phase current generated by the He Dreiht offshore wind farm will be converted into direct current and transported to the mainland with an approximately 120-kilometer-long sea cable.

From the landfall in Hilgenriedesiel, the electricity will be transmitted along 110 kilometers of underground cable to the future converter station Garrel/Ost in the Cloppenburg area.

BorWin epsilon is expected to be commissioned by the end of 2025.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingDeepwater InstallationGridOffshore WindSubseaVessels & VehiclesBusiness Developments & ProjectsInfrastructureOperations & MaintenanceProject & TendersVessels

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norwegian PSV to continue current charter for additional 100 days
  2. 2Italy’s NextGeo to open office in Germany
  3. 3TotalEnergies finds more oil off Angola, enters two exploration blocks
  4. 4Odfjell Drilling’s new rig busy until 2031 thanks to deal with Vår Energi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free