Home›Cabling›Subsea interconnector between two Canary Islands crosses finish line (Video)
Cabling

February 12, 2026 · about 7 months ago

Subsea interconnector between two Canary Islands crosses finish line (Video)

Spanish transmission system operator (TSO) Red Eléctrica has completed the interconnection between the islands of Tenerife and La Gomera in Spain, reinforcing the security of supply in the Canary Islands. The interconnection consists of a 66 kV double-circuit line, with a 36-kilometer underwater sec

1 minutes read
  • LinkedIn
  • X
  • Email
Subsea interconnector between two Canary Islands crosses finish line (Video)
Source: Red Eléctrica

Spanish transmission system operator (TSO) Red Eléctrica has completed the interconnection between the islands of Tenerife and La Gomera in Spain, reinforcing the security of supply in the Canary Islands.

The interconnection consists of a 66 kV double-circuit line, with a 36-kilometer underwater section and two underground sections at both ends, which connect two new substations at El Palmar in La Gomera and Chío in Tenerife.

According to Red Eléctrica, the submarine section runs at a maximum depth of 1,145 meters, making it the deepest 66 kV AC three-core submarine link in the world, which required an adapted cable design, reinforced with lightweight materials capable of withstanding the demanding requirements of the environment in which the cable was installed.

This content is available after accepting the cookies.

Prysmian’s cable laying vessel (CLV) Cable Enterprise began laying the cable on August 29, 2025 , ahead of schedule due to favorable sea conditions, completing it in two voyages from San Sebastián de La Gomera to Punta Blanca in Tenerife, as announced in September 2025 .

Prysmian is also in charge of the design, supply, installation and commissioning of the interconnection between the Spanish mainland and Ceuta, a Spanish city on the north coast of Africa. The CLV Giulio Verne began offshore operations on the first of two submarine circuits that will connect Ceuta with the Spanish mainland on August 26, 2025.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureOutlook & StrategyProject & Tenders

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1SED Energy Holdings and Ventura Offshore to unite into one
  2. 2New Boskalis rock installation vessel starts work offshore Poland
  3. 321 companies apply for Norway’s new oil & gas exploration areas
  4. 4Spanish shipyard launches its largest-ever vessel, built for Østensjø Rederi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free