Home›Cabling›First of 7 transformers delivered for first UK-Germany energy link
Cabling

February 19, 2026 · about 6 months ago

First of 7 transformers delivered for first UK-Germany energy link

Siemens Energy has delivered the first of seven transformers that will help to power NeuConnect, the first energy link between the UK and Germany. The transformer was taken from Siemens Energy’s factories in Nürnberg, Germany, and delivered by barge along the Rhine River to Rotterdam, the Netherland

2 minutes read
  • LinkedIn
  • X
  • Email
First of 7 transformers delivered for first UK-Germany energy link
Source: NeuConnect

Siemens Energy has delivered the first of seven transformers that will help to power NeuConnect, the first energy link between the UK and Germany.

The transformer was taken from Siemens Energy’s factories in Nürnberg, Germany, and delivered by barge along the Rhine River to Rotterdam, the Netherlands, before being shipped by sea to the UK and then taken by road to the Isle of Grain site.

The structure is 7 meters long, 5 meters tall and weighs more than 200 tons. Further transformers will be delivered to the UK over the coming months.

NeuConnect CEO Arnaud Grévoz said: “We have made a strong start to 2026 in our construction works, and the arrival of the first transformer in the UK marks another important milestone as we take delivery of key equipment that will help to power this vital new energy link. With our Converter Stations taking shape and cabling work continuing in UK waters, we remain firmly on track.”

Related Articles

Cabling

‘Another vital piece of the jigsaw’ comes together for first UK-Germany energy link

2 min read

Led by global investors Meridiam, Allianz, Kansai Electric Power and TEPCO, the 725-kilometer NeuConnect will create an “invisible energy highway” capable of transferring 1.4 GW of electricity, enough to power 1.5 million homes, in either direction, with converter stations on the Isle of Grain in Kent and Wilhelmshaven in northern Germany.

Construction work at the UK site on the Isle of Grain began in the summer of 2023 , with construction in Germany following in May 2024 .

Onshore in the UK, ‘super structure’ works have reached full height on the 24-meter-high, 70-meter-wide converter hall buildings, with cladding works well underway. As for work offshore, Prysmian’s cable laying vessel (CLV) Leonardo da Vinci is in UK waters, where it will install over 140 kilometers of subsea cabling over the coming months.

This latest phase of works will see cabling completed in UK waters and start to move into Dutch waters.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureOutlook & StrategyProject & TendersTransitionVision

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1SED Energy Holdings and Ventura Offshore to unite into one
  2. 2New Boskalis rock installation vessel starts work offshore Poland
  3. 321 companies apply for Norway’s new oil & gas exploration areas
  4. 4Spanish shipyard launches its largest-ever vessel, built for Østensjø Rederi

Home of Energy Transition

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free