To connect an offshore wind farm to the electricity network, electrical infrastructure will be needed both onshore and offshore. For Triton Knoll, this is likely to include: – offshore cables running from the offshore wind farm to land on the Lincolnshire coast and underground cables running from th
To connect an offshore wind farm to the electricity network, electrical infrastructure will be needed both onshore and offshore. For Triton Knoll, this is likely to include: – offshore cables running from the offshore wind farm to land on the Lincolnshire coast and underground cables running from th
In early September the London Array Consortium started installing London Array’s last export cable. The export cables run from offshore substations to the onshore substation at Cleve Hill, where the power generated by London Array will flow into the national electricity network. The cables have been
Anbaric Transmission has been monitoring the recent German draft legislation about connecting offshore wind parks to the onshore grid and has offered its views about how to finance the offshore grid connections at the lowest possible cost to the German public. However, contrary to recent press repor
National Grid has begun its first stage of consultation on proposals to connect new sources of low-carbon electricity generation in North Wales. A new nuclear power station at Wylfa and an offshore wind farm in the Irish Sea are being proposed by Horizon Nuclear Power and Celtic Array respectively.
Danish marine technology company MacArtney has developed a wet-mate connector, which is a new way to connect and disconnect power. The wet-mate connector is a 1kV device that enables two power cables to be linked together underwater. According to Social.tidaltoday.com, the project was successfully d
Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has today received planning permission from Breckland Council to build and operate an onshore substation near Necton, Norfolk, together with an associated buried cable route spur. The substation is needed to connect the Dud
Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has today received planning permission from Breckland Council to build and operate an onshore substation near Necton, Norfolk, together with an associated buried cable route spur. The substation is needed to connect the Dud
Anbaric, a U.S. transmission company involved in smart grids, subsea cabling, as well as renewables, is said to be considering buying a share in TenneT. Wirtschaftswoche magazine informed on Saturday about Anbaric’s plans to invest USD 4 billion in the German transmission operator. TenneT and German
GL Renewables Certification (GL RC) has issued a component certificate to SCADA International for its power plant controller. The GL RC certificate confirms that the power plant controller meets the requirements of the FGW (Federation of German Windpower and other Renewable Energies). The certificat
GL Renewables Certification (GL RC) has issued a component certificate to SCADA International for its power plant controller. The GL RC certificate confirms that the power plant controller meets the requirements of the FGW (Federation of German Windpower and other Renewable Energies). The certificat
After securing and successfully completing two major cable projects in the Irish Sea, and a further fault investigation on an Interconnector underway, the joint venture of Osiris Marine Services and Nordic Offshore Marine look to the spot charter market to provide a cost effective solution to subsea
Intertek’s Energy and Water consultancy (formerly Intertek METOC), is to act as Technical Project Manager for surveys to TenneT, the European electricity grid operator, on its German offshore wind connections. The work will see Intertek design and manage geophysical and geotechnical surveys for the
Bangor Hydro Electric Company has verified on September 13 that electricity is being delivered to their power grid from Ocean Renewable Power Company’s (ORPC’s) Cobscook Bay Tidal Energy Project. This is the first power from any ocean energy project including offshore wind, wave and tidal, to be del