Atlantic Wind Transfers’ new crew transfer vessel (CTV) Atlantic Endeavor has begun working at the Coastal Virginia Offshore Wind (CVOW) project. Blount Boats launched the Chartwell 24 CTV the day after Christmas, after which the vessel spent three days going through sea trials and USCG inspections.

The 731.5 MW Borssele 3 & 4 wind farm off the Netherlands will be officially handed over to the Operations team on Thursday, 18 February, as all construction phase-related activities have been completed and the wind farm is now generating electricity in full capacity. The first of the project’s 77 M

The second inter-array cable installation campaign will begin this month at the Moray East offshore wind farm, where the seventh wind turbine was installed on 10 February and the decommissioning of the met mast is currently underway. The first inter-array cable installation campaign, which started o

The Offshore Wind Growth Partnership (OWGP), established as part of the Offshore Wind Sector Deal and funded by members of the Offshore Wind Industry Council (OWIC), has awarded twelve UK companies a total of GBP 1.3 million (around € 1.5 million) in funding and business improvement support. “These

Global financial investment for offshore wind set a new record in 2020 with USD 30 billion, surpassing the previous high of USD 22 billion from 2018, according to The Renewables Consulting Group (RCG). According to RCG’s Global Renewable Infrastructure Projects (GRIP) database, the total capacity fi

Royal HaskoningDHV has been awarded a contract for environmental consultancy services for NortH2, a large offshore wind-to-hydrogen project being developed by a consortium comprising Shell, Gasunie, Equinor, and RWE, and supported by Groningen Seaports and Province of Groningen. “We are thrilled to

The Danish Energy Agency (DEA) and the Danish Environmental Protection Agency are holding a five-week public hearing concerning the environmental assessments for Hesselø offshore wind project. The public, companies, authorities and other interested parties are invited to submit ideas on the strategi

Crown Estate Scotland has delayed the deadline for applications for ScotWind offshore wind leasing and is carrying out a review of the option structure for the process. The review of the option structure follows the announcement of the results of The Crown Estate’s offshore wind leasing auction for

Around 20 per cent of foundations has been installed at the 1.4 GW Hornsea Two, which is soon to become the world’s largest offshore wind farm, Ørsted said. The export cable installation works are on schedule and turbine installation is set to commence in the second half of this year, the project’s

Ørsted has selected Atlantique Offshore Energy, part of Chantiers de l’Atlantique, to provide the complete design and construction of the electrical offshore substation for the Gode Wind 3 offshore wind project. Atlantique Offshore Energy will execute the full engineering, procurement, construction

Siemens Gamesa and the CrossWind joint venture between Shell and Eneco have executed the contract to deliver the turbines for the 759 MW Hollandse Kust Noord offshore wind farm in the Dutch North Sea. The contract includes the supply of 69 SG 11.0-200 DD offshore wind turbines and a 15-year service

The Carbon Trust’s Offshore Wind Accelerator (OWA) has published new recommendations for fibre optic cable design to mitigate the risk of export cable failure in offshore wind. The five key recommendations are: The optical fibres should be encompassed by a stainless steel tube and stainless-steel wi

Another company involved in the oil & gas sector has set its sights on offshore wind, as the industry increasingly moves towards renewable energy amid the global energy transition. The latest to announce its clean energy plans is BW Offshore, which is now in investment discussions with the floating

DNV GL has officially issued the project certificate to Vattenfall for its Horns Rev 3 offshore wind farm in Denmark. The certification covered the turbines including their support structure plus all the cabling connecting them to the offshore substation. Inspections were carried out over a three-ye