TenneT is looking for a contractor who will carry out horizontal directional drilling (HDD) works for the connection of the Hollandse Kust Zuid wind farm area.
Ørsted has invited comments on the proposed modifications to the onshore and offshore export cable corridor for the Hornsea Project Three wind farm located some 120 kilometres off the north Norfolk coast, UK.
Belgian offshore wind developer Otary has issued a tender for engineering, procurement, construction, and installation (EPCI) of high voltage substations on the Seastar and the Mermaid offshore wind farms.
South Korean Tamra offshore wind farm was officially opened today (17 November) at a ceremony attended by South Korea’s Minister of Trade, Industry and Energy, Paik Ungyu, and the officials from Korea South-East Power, the wind farm’s developer.
South Korean Tamra offshore wind farm was officially opened today (17 November) at a ceremony attended by South Korea’s Minister of Trade, Industry and Energy, Paik Ungyu, and the officials from Korea South-East Power, the wind farm’s developer.
Otary, the developer of Seastar and Mermaid offshore wind farms to be built off the coast of Belgium, is looking for EPCI contractor(s) for 225 kV XLPE submarine high voltage cables and connections between the wind farms’ substations and the Belgian modular offshore grid.
Inch Cape Offshore Limited (ICOL) has used a 3D model created by SLR to communicate plans for the proposed 784MW Inch Cape offshore wind farm off the coast of Angus, Scotland.
A2Sea’s jack-up vessel Sea Challenger has started installing transition pieces at the 396MW Merkur offshore wind farm located off the coast of Germany.
A2Sea’s jack-up vessel Sea Challenger has started installing transition pieces at the 396MW Merkur offshore wind farm located off the coast of Germany.
The UK-based specialist insurer of pension funds Pension Insurance Corporation (PIC) has invested GBP 115 million to provide debt-financing for the acquisition of a 50% share in the 659MW Walney Extension offshore wind farm.
The European Investment Bank (EIB) has approved project financing for the Blauwwind offshore wind farm located in the Borssele III and IV zones in the Dutch part of the North Sea.
The Regional Administrative Tribunal of Sicily (Il Tribunale Amministrativo Regionale per la Sicilia – TAR) has revoked a construction permit granted by the Italian Ministry for the Environment, Land and Sea (IMELS) for the 137MW offshore wind project in the Gulf of Gela off Sicily’s southern coast.
The Regional Administrative Tribunal of Sicily (Il Tribunale Amministrativo Regionale per la Sicilia – TAR) has revoked a construction permit granted by the Italian Ministry for the Environment, Land and Sea (IMELS) for the 137MW offshore wind project in the Gulf of Gela off Sicily’s southern coast.
RTS Wind is currently involved in the commissioning works at the 350MW Wikinger offshore wind farm located in the German Baltic Sea.