The progress on Walney 2 has been dramatically reduced due to windy weather conditions for the last couple of weeks. Heavy winds and high waves have paused the commissioning activities at Walney 2, making it impossible to access the turbines. When the wave height exceeds certain limits, all personne
The establishment of the future operation and maintenance facilities has now come so far that flag and garland could be hoisted on the communication tower to mark the roofing ceremony. Approx 30 workmen, representatives from the harbour, consultants and DONG Energy’s project group were present. Thom
The establishment of the future operation and maintenance facilities has now come so far that flag and garland could be hoisted on the communication tower to mark the roofing ceremony. Approx 30 workmen, representatives from the harbour, consultants and DONG Energy’s project group were present. Thom
The London Array consortium, Abu Dhabi’s Masdar, E.ON, Dong Energy on Monday announced that work is under way at the world’s largest offshor… (wam) [mappress] Source: wam, November 01, 2011
The London Array consortium, Abu Dhabi’s Masdar, E.ON, Dong Energy on Monday announced that work is under way at the world’s largest offshor… (wam) [mappress] Source: wam, November 01, 2011
The innovative elastometric spring bearings designed to improve the vertical load carrying capacity of the wind turbines of the Sheringham Shoal Offshore Wind Farm, have now been installed on each of the 90 foundations at the site, 20 kilometres off the coast of the Norfolk in the UK. Trelleborg Off
The innovative elastometric spring bearings designed to improve the vertical load carrying capacity of the wind turbines of the Sheringham Shoal Offshore Wind Farm, have now been installed on each of the 90 foundations at the site, 20 kilometres off the coast of the Norfolk in the UK. Trelleborg Off
All foundations of the offshore wind farm Thornton Bank 2 has been successfully installed off the coast of Belgium. The installation work started in June this year and has been accomplished on schedule. In total, 25 jacket foundations for the wind turbines and one offshore transformer station have b
The personnel are working flat out to complete the O&M buildings at Grenaa Harbour. The assembly of the elements for the future welfare and administration building is almost complete, and the shape of the building now looks like the outline on the site sign. The next step is the light external wall
The personnel are working flat out to complete the O&M buildings at Grenaa Harbour. The assembly of the elements for the future welfare and administration building is almost complete, and the shape of the building now looks like the outline on the site sign. The next step is the light external wall
DONG Energy has signed an agreement with the Danish Fishermen’s Association on compensation for loss of earnings from fishing in connection with the construction of Anholt Offshore Wind Farm. The working area will be cordoned off for unauthorised persons during the construction, and there will be no
The Nordic Investment Bank (NIB) and Danish energy company DONG Energy have signed a loan totalling EUR 240 million ($328 million) for financing the Anholt offshore wind farm. The loan has a maturity of 10 years and will partly finance the construction of what will become one of the world’s largest
During September, the installation activities have been slowed down due to adverse weather, and last week only had one working day, which was used to full extent to install one array cable and the third last wind turbine. After the installation, Kraken headed for the Harbour of Mostyn to get the las
Essen based renewable energy developer, RWE Innogy, is looking for contractor do design, engineering, construct, supply and install the Innogy Nordsee 1(“IN1”) 155/33 kv substation including platform, substructure and foundation. Innogy Nordsee 1 is the largest single project RWE has undertaken so f