Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›FPSO›Fortuna FLNG construction contract awarded
FPSO

May 10, 2017 · about 9 years ago

Fortuna FLNG construction contract awarded

Following last week’s umbrella agreement for the Fortuna FLNG project off Equatorial Guinea, a construction contract has been awarded for conversion of an LNG carrier to a floating liquefaction facility (FLNG). Ophir Energy informed on Wednesday that Golar LNG Limited has executed amended and novate

2 minutes read
  • LinkedIn
  • X
  • Email

Following last week’s umbrella agreement for the Fortuna FLNG project off Equatorial Guinea, a construction contract has been awarded for conversion of an LNG carrier to a floating liquefaction facility (FLNG).

Ophir Energy informed on Wednesday that Golar LNG Limited has executed amended and novated agreements for conversion of the 126,000m3 LNG carrier Gandria.

Ophir further said that the primary contract for the FLNG Gandria was entered into with Singapore’s Keppel Shipyard Limited. Black & Veatch will provide its licensed PRICO technology, perform detailed engineering and process design, specify and procure topside equipment, and provide commissioning support for the FLNG topsides and liquefaction process.

The Gandria vessel will be acquired by the Fortuna Joint Operating Company (JOC) upon reaching the planned Final Investment Decision (FID) in mid-2017. The Republic of Equatorial Guinea has the right to acquire up to 30% of the vessel.

OneLNG, a joint venture between Golar and Schlumberger, and Ophir have 66.2% and 33.8% ownership of the JOC, respectively.

The award of the Midstream EPC contracts completes another milestone required for FID. At this point three external milestones remain: the award of the Upstream EPCIC contracts; the completion of the debt facility; and the award of LNG offtake.

According to the company, the award of the EPCIC contract is on schedule and term sheets have been agreed with a consortium of China-based lenders. The counter-parties to the financing have now entered into final documentation stage. Also, the Fortuna partners will determine in May the structure and amount of the expected 2.5MMTPA to place under contract at FID. An award of offtake will be made from the shortlist of attractive proposals from high quality counterparties.

Nick Cooper , CEO of Ophir Energy commented: “The award of the Midstream construction completes another milestone as we approach FID. We remain firmly on schedule for the FID of Africa’s first deep water FLNG Project in mid-2017.”

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FPSOBusiness & FinanceInfrastructure

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free