Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›FPSO›Samsung Heavy confirms Egina FPSO sailaway
FPSO

November 2, 2017 · about 9 years ago

Samsung Heavy confirms Egina FPSO sailaway

As previously reported by Offshore Energy Today and now confirmed by the builder, the giant FPSO left the shipyard on Tuesday, October 31.

2 minutes read
  • LinkedIn
  • X
  • Email

South Korean shipbuilder Samsung Heavy Industries (SHI) has confirmed that Total’s Egina FPSO has sailed away from its Geoje shipyard, heading to Nigeria.

As previously reported by Offshore Energy Today and now confirmed by the builder, the giant FPSO left the shipyard on Tuesday, October 31. It will take three months for it to reach Nigeria, according to SHI’s statement on Wednesday.

SHI won the order to build Egina FPSO in 2013.

The FPSO, operated by Total, is 330 meters in length, 61 meters across and 34 meters high, with a storage capacity of 2.3 million barrels of oil.

Egina FPSO project is under the Nigerian local content regulations, and a portion of the topsides fabrication and integration is to be completed in Nigeria.

SHI said that the remaining topside module integration and commissioning will take place in Nigeria for scheduled delivery in the second half of 2018.

SHI earlier formed a joint venture (SHI-MCI) with a Nigerian local company and established a production facility in Lagos, Nigeria to meet the local content requirements.

Following completion, the FPSO will be moored at the Total-operated Egina oil field, located some 130 km off the coast of Nigeria at water depths of more than 1,500 meters.

Apart from the FPSO, infrastructure on the field will consist of an oil offloading terminal, and subsea production systems that will include 52 kilometers of oil and water injection flowlines, 12 flexible jumpers, 20 kilometers of gas export pipelines, 80 kilometers of umbilicals, and subsea manifolds.

SHI has now completed delivery or sail-away of three massive offshore projects. Namely, the Ichthys CPF , the world’s largest floating gas processing facility, was delivered in April and Prelude FLNG , the world’s largest FLNG, left Geoje in June.

Offshore Energy Today Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FPSOInfrastructureProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free