Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›FPSO›Africa’s first FLNG unit in place. Production to start by 2017 end
FPSO

November 30, 2017 · about 8 years ago

Africa’s first FLNG unit in place. Production to start by 2017 end

World’s first converted FLNG unit, and soon to be Africa’s first FLNG unit producing LNG from an offshore gas field, has reached its final location in Cameroon, after a long journey from Singapore.

2 minutes read
  • LinkedIn
  • X
  • Email

World’s first converted FLNG unit, and soon to be Africa’s first FLNG unit producing LNG from an offshore gas field, has reached its final location in Cameroon, after a long journey from Singapore.

Golar on Thursday informed that the FLNG Hilli was on site in Cameroon “with production expected to commence shortly.”

Converted from a large LNG carrier, – the Hilli Episeyo – the world’s first converted FLNG vessel – was delivered to Golar early in October, after which it left Singapore.

The 293 meters long vessel will be moored and connected to an offshore gas field, from which it will take gas and convert it to LNG for exports, making it the first operational FLNG unit in Africa.

The Hilli Episeyo, unit will be put in operation offshore Kribi, Cameroon for Société Nationale des Hydrocarbures and Perenco Cameroon.

According to Golar’s statement on Thursday, the Hilli arrived in Cameroon on November 20, 2017 and hook-up and connection to risers and umbilicals is now underway.

Golar said that the following period would see tendering of a Notice of Readiness, which triggers commissioning rate toll fees. A ship-to-ship transfer of LNG for commissioning purposes will be carried out, followed by the start of the full commissioning process.

“As part of this process, Golar anticipates production of first commercial LNG to take place around year end. Final commissioning is expected to complete during the second half of 1Q 2018 and the project remains well within budget,” Golar said.

Hilli Episeyo was converted from the 1975-built Moss LNG carrier with a storage capacity of 125,000 m3. It was designed for a liquefaction capacity of about 2.4 million tonnes of LNG per annum.

The vessel recently became part of the first commercial Liquefied Natural Gas (LNG) bunker transfer in Singapore . Namely, FueLNG, a joint venture between Keppel and Shell Eastern Petroleum (Pte) Ltd (Shell), completed truck-to-ship bunkering for the FLNG vessel.

Offshore Energy Today Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FPSOInfrastructure

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy’s CEO: Repairs on damaged LNG trains to take three years
  2. 2Remote operations center for unmanned survey operations opens in Singapore
  3. 3Australian oil & gas firm makes its first foray into Liberia’s deepwater arena
  4. 4Brazilian subsea services provider changes hands

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free