Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Equinor concludes Hammerfest LNG fire review
Clean Fuel

May 12, 2021 · about 5 years ago

Equinor concludes Hammerfest LNG fire review

Norwegian oil major Equinor has concluded the internal investigation into the incident that happened at the Hammerfest LNG facility in September 2020.

2 minutes read
  • LinkedIn
  • X
  • Email
Equinor concludes Hammerfest LNG fire review
Courtesy of Øivind Haug / Equinor

Norwegian oil major Equinor has concluded the internal investigation into the incident that happened at the Hammerfest LNG facility in September 2020.

The company has also concluded the internal investigation into the incident that occured at the Tjeldbergodden industrial facility at Nordmøre in Decemeber 2020.

Speaking of the two incidents, Irene Rummelhoff , Equinor’s executive vice president, Marketing, Midstream & Processing, said that both fires at the onshore facilities were very serious.

Both incidents also triggered a comprehensive improvement effort within safety at the onshore facilities.

The Norwegian Petroleum Safety Authority has already concluded its review and noted serious breaches of safety regulations.

Related Articles

Clean Fuel

PSA wraps up Hammerfest LNG fire investigation

1 min read

In the incident that occurred on 28 September, 2020 , a fire occurred in the filter housing on gas turbine generator 4 at Hammerfest LNG during the start-up of the facility.

The investigation group notes that the cause of the fire was spontaneous ignition in the filters in the turbine’s air inlets, caused by excessively high temperature over a long period of time.

The anti-icing heat exchanger in the air inlet was used outside of its intended area of application, thus causing the high temperature that triggered the fire. The investigation group does not believe that the maintenance interval for exchanging the filters that self-ignited is a contributing cause.

The fire was restricted to the filter housing on gas turbine generator 4 and the investigation group concludes that there was no major accident potential as regards personal injuries. Both the PSA report and Equinor’s own investigation confirm that the fire was unlikely to spread to other parts of the facility.

Due to the scope of repairs needed to restore the facility to safe production, Equinor has already delayed the restart of the Hammerfest LNG facility to March 2022 .

Initially, the restart was scheduled for 1 October 2021.

Equinor has initiated modifications to the air intakes in the turbines to prevent similar incidents from occurring.

The incident was not caused by a single technical or human error but was the result of several direct and underlying factors.

Equinor is added it is following up all the orders and nonconformities in the Petroleum Safety Authority’s investigation of the fire, and will present a plan to the PSA for complying with the orders by 1 June 2021.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelLNGBusiness Developments & ProjectsOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free