Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Marine Energy›Jones Bros nears completion of infrastructure works for Morlais tidal power scheme
Marine Energy

July 25, 2023 · about 3 years ago

Jones Bros nears completion of infrastructure works for Morlais tidal power scheme

North Wales-based company Jones Bros Civil Engineering has made progress on the construction of onshore infrastructure for the Morlais tidal energy project and is now on track to complete the works ahead of original schedule.

2 minutes read
  • LinkedIn
  • X
  • Email
Works underway to bring Morlais tidal power scheme online (Courtesy of Menter Môn)
Works underway to bring Morlais tidal power scheme online (Courtesy of Menter Môn)

North Wales-based company Jones Bros Civil Engineering has made progress on the construction of onshore infrastructure for the Morlais tidal energy project and is now on track to complete the works ahead of original schedule.

Jones Bros is nearing completion of the works at the landfall substation close to Tŷ Mawr Mynydd in Holyhead, according to Menter Môn , a social enterprise in charge of the Morlais scheme.

The works started in spring 2022, after Jones Bros secured €28.5 million contract for the construction of the landfall substation on Holy Island, as well as cabling which will connect the scheme to the UK’s electricity transmission network National Grid.

According to Menter Môn, the works are expected to be finished by fall 2023, which is sooner than originally scheduled.

Related Articles

Marine Energy

Jones Bros secures €28.5 million contract for Morlais tidal onshore works

2 min read

Cabling to connect the substation to the grid in Parc Cybi has also been completed which has brough an end to local road closures.

Stockton Drilling’s horizontal directional drilling (HDD) work in South Stack, an island situated just off Holy Island on the northwest coast of Anglesey, has also been completed, Menter Môn informed.

To remind, Morlais tidal energy project secured €37.6 million of grant funds from the EU’s regional funding program back in March 2022.

Located off the northwest coast of Holy Island, the consented area for the installation and commercial demonstration of multiple arrays of tidal energy devices will be suitable for a maximum installed capacity of 240MW.

Once fully operational, the Morlais scheme will be able to provide clean power for over 180,000 homes.

Subscribe and follow

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Marine EnergySubseaTidal & Wave EnergyBusiness Developments & ProjectsInfrastructureOutlook & StrategyRegulation & Policy

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Expro lines up 14-well Canadian offshore life-extension campaign
  2. 2TotalEnergies greenlights gas project to feed one-third of Nigeria LNG train expansion
  3. 3Construction ramps up at Orkney Islands’ first link to UK mainland
  4. 4Perenco on offshore platform electrification quest to power Brazil’s shallow-water fields from shore

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free