Seabed preparation activities are scheduled to begin at the Inch Cape offshore wind farm site in Scotland at the end of March. N-Sea, which has been contracted for the job, will start the work within the array site and the export cable corridor on or around March 30 and continue until November 2025.

Bluestream Offshore, a subsidiary of OEG Energy, has been awarded a contract by transmission system operator (TSO) TenneT for the retrofit installation of a corrosion protection system on the SylWin alpha offshore converter station for the SylWin1 offshore grid connection in Germany. The award is fo