The installation of the 80th turbine in the BARD Offshore 1 construction site this week, one month earlier than originally planned, marks the official completion of the installation process for the first commercial offshore wind farm in the North Sea. The BARD Group has thus affirmed its role as a p
Centrica Energy’s Lincs offshore wind farm has today (Thursday) been officially opened by the Deputy Prime Minister Nick Clegg. The last of the wind farm’s 75 wind turbines was connected to the National Grid on Wednesday 24th July, bringing the 270MW project up to full strength for the first time. L
Centrica Energy’s Lincs offshore wind farm has today (Thursday) been officially opened by the Deputy Prime Minister Nick Clegg. The last of the wind farm’s 75 wind turbines was connected to the National Grid on Wednesday 24th July, bringing the 270MW project up to full strength for the first time. L
54 of 108 monopile foundations and transition pieces have now been installed at the West of Duddon Sands offshore wind farm, a 50/50 joint venture between DONG Energy and ScottishPower Renewables. On Saturday 27th July, the West of Duddon Sands team complete installation of the 54th transition piece
Parker Hannifin Corporation, the global leader in motion and control technologies, assisted in the installation of monopiles and transition pieces for the Meerwind offshore wind project. Parker Maritime, a business unit of Parker’s Energy Products Division, provided the Seajacks team with navigation
The second cable installation phase at the Global Tech I offshore wind farm has started. The first cables have already been laid between the foundations and pulled into them, and now it is time for them to be flushed into the ocean floor by the installation vessel Cable Innovator and its Remotely Op
Vattenfall, the European energy company, is to invest in leading radar technology to enable construction of an offshore wind farm in what is believed to be a world first deal. The contract, with American firm C Speed, heralds the world’s first ever permanent installation of a fully wind farm-capable
The next major step has been taken at the DanTysk offshore wind farm – a first cable has been laid between foundations 39 and 40. The sea conditions were perfect for executing this operation for the first time on DanTysk. It did not go smoothly the entire time. Some wires broke and had to be [&helli
EWE, the developer of Riffgat offshore wind farm, has announced that the construction of its project is now completed. After being significantly involved in the construction of the first German offshore wind test Alpha Ventus, the company has now built Riffgat offshore wind farm ‒ the first commerci
EWE, the developer of Riffgat offshore wind farm, has announced that the construction of its project is now completed. After being significantly involved in the construction of the first German offshore wind test Alpha Ventus, the company has now built Riffgat offshore wind farm ‒ the first commerci
The Planning Inspectorate has announced that the application from Channel Energy Ltd for the proposed Atlantic Array offshore wind farm has been accepted, by the Secretary of State for Communities and Local Government, for examination. The application for the proposed offshore wind farm was submitte
The Planning Inspectorate has announced that the application from Channel Energy Ltd for the proposed Atlantic Array offshore wind farm has been accepted, by the Secretary of State for Communities and Local Government, for examination. The application for the proposed offshore wind farm was submitte
The 155/33-kilovolt offshore substation and jacket are ready to leave the construction yard of Strukton Hollandia in Krimpen aan den IJssel near Rotterdam any day now. The jacket will provide a platform for the substation 45m above the seabed in a water depth of 26m. Their final destination is 70km
RWE npower renewables welcomes today’s announcement that consent has been awarded for the turbines at Triton Knoll Offshore Wind Farm. The Secretary of State for Energy and Climate Change has granted consent for up to 288 offshore wind turbines to be located off the East Coast of England. The projec