The New York State Energy Research and Development Authority (NYSERDA) has finalized contracts for the Empire Wind and Sunrise Wind offshore wind projects. NYSERDA signed 25-year OREC purchase-and-sale agreements with the joint venture of Ørsted A/S and Eversource Energy for its 880MW Sunrise Wind a
The New York State Energy Research and Development Authority (NYSERDA) has finalized contracts for the Empire Wind and Sunrise Wind offshore wind projects. NYSERDA signed 25-year OREC purchase-and-sale agreements with the joint venture of Ørsted A/S and Eversource Energy for its 880MW Sunrise Wind a
First Subsea has secured a second contract with Spain’s Cobra Group to provide Cable Protection Systems (CPSs) for the 50MW Kincardine floating wind farm offshore Scotland. First Subsea provided CPSs for the first Kincardine floating wind turbine which was installed 15 kilometres off the coast, sout
Portugal’s ASM Industries has tested and floated out the first of the two floating foundations being built for the 25MW WindFloat Atlantic wind farm. “The tests were very successful and totally safe, and were the culmination of several months of hard and continuous work,” Adelino Costa Matos, CEO of
The first WindFloat Atlantic turbine has arrived at its final destination off the coast of Viana do Castelo in Portugal. The fully-assembled platform and its 8.4MW MHI Vestas turbine set off from the Spanish Port of Ferrol towards its final destination 20km off the coast of Viana do Castelo yesterda
US offshore wind developer Vineyard Wind has formed a partnership with Marmon Utility for the establishment of manufacturing capabilities at Marmont’s Connecticut facility producing Kerite cables to supply some or all of the inter-array cable cores for the Park City Wind project. The agreement will
EEW Offshore Structures Britain (OSB) has completed the load-out of the first six transition pieces built for the Borssele 1+2 offshore wind farm in the Dutch North Sea. The Teesside-based company will manufacture and deliver a total of 35 transition pieces for Ørsted’s 752MW wind farm. ALE Heavy Li
Swedish energy company Vattenfall and its partner Wallenstam have cancelled the Taggen offshore wind project in Sweden after the Swedish Armed Forces said no to the wind farm. ”Of course, it is regrettable that we are now forced to put down a large renewable energy project that we, together with Wal
Jumbo’s heavy-lift carrier has arrived at Steelwind Nordenham’s quayside to pick up the first four monopiles destined for the Yunlin offshore wind project in Taiwan. According to Steelwind, the Jumbo Jubilee arrived at the heavy-lift terminal Blexen, Germany, on 19 October and the loadout operations
Jumbo’s heavy-lift carrier has arrived at Steelwind Nordenham’s quayside to pick up the first four monopiles destined for the Yunlin offshore wind project in Taiwan. According to Steelwind, the Jumbo Jubilee arrived at the heavy-lift terminal Blexen, Germany, on 19 October and the loadout operations
The first WindFloat Atlantic platform with the turbine fully installed has set off from the Spanish Port of Ferrol towards its final destination 20 kilometres off the coast of Viana do Castelo in Portugal. Once at the final location, the three floating structures –stretching 30 metres in height and
Van Oord’s offshore installation vessel Aeolus has arrived at the Sif terminal in Rotterdam to load the first monopiles for the 731.5MW Borssele III & IV offshore wind farm. The load out of the monopiles for the Borssele III & IV offshore wind farm is currently being prepared at the Sif Rotterdam ya
The first offshore substation transition piece and J-tube cage for the SeaMade offshore wind farm are on their way from Belgium to the Sif terminal in Rotterdam, the Netherlands, DEME Group said. The transition piece was loaded out at Smulders’ yard in Hoboken. Together with the foundation, which is
Equinor and the Snorre and Gullfaks partners have submitted updated development plans to the Norwegian government for the Hywind Tampen floating wind farm. The Hywind Tampen floating offshore wind farm will consist of 11 8MW wind turbines located some 140 kilometres from shore in 260-300 metres of w