Eolien Maritime France, a subsidiary of EDF EN and Dong Energy, is looking to award contracts for the manufacturing and additional construction work of foundations for two proposed offshore wind farms off the French coast. Some 75 monopiles and associated transition pieces will be needed for the Cou
Work on E.ON’s Humber Gateway Offshore Wind Farm is well underway, according to data from KIS-ORCA. Inter-array cables are being installed by the ‘Atlantic Carrier’, while 0Fugro Saltire’ is working on cable burial. ‘Stemat Spirit’ has also joined the project for cable installation and will stay on
Work on E.ON’s Humber Gateway Offshore Wind Farm is well underway, according to data from KIS-ORCA. Inter-array cables are being installed by the ‘Atlantic Carrier’, while 0Fugro Saltire’ is working on cable burial. ‘Stemat Spirit’ has also joined the project for cable installation and will stay on
The Bathymetric Survey at the Robin Rigg offshore wind farm is now complete and the 12 meter Catamaran ‘Norfolk Swift’ has demobilised from this site. A general maintenance programme will continue with the transfer of technicians out to selected turbines by Crew Transfer Vessels (CTVs) on a daily ba
From autumn 2016, A2SEA will play a key role in helping build the 402MW Dudgeon Offshore Wind Farm in the UK for Statoil, Masdar and Statkraft. A2SEA will provide their specialist purpose-built offshore installation vessel SEA INSTALLER to install the 67 Siemens 6MW turbines. Dudgeon Offshore Wind F
From autumn 2016, A2SEA will play a key role in helping build the 402MW Dudgeon Offshore Wind Farm in the UK for Statoil, Masdar and Statkraft. A2SEA will provide their specialist purpose-built offshore installation vessel SEA INSTALLER to install the 67 Siemens 6MW turbines. Dudgeon Offshore Wind F
RES Offshore has successfully completed its first Engineer Procure Construct (EPC) contract for the design and installation of Met Mast for the West of Duddon Sands Offshore Wind Farm. Having been awarded the contract in June 2013, RES has project managed the design, fabrication and installation of
RES Offshore has successfully completed its first Engineer Procure Construct (EPC) contract for the design and installation of Met Mast for the West of Duddon Sands Offshore Wind Farm. Having been awarded the contract in June 2013, RES has project managed the design, fabrication and installation of
Offshore WIND’s photo of the day: Load out of foundations for the Eneco Luchterduinen offshore wind farm. The photo, sent to Offshore WIND by a reader, captures a moment of the load out work done yesterday (October 13) at the Port of Vlissingen from the Aeolus vessel, which is owned and operated by
Forewind has started a consultation on two minor proposed changes to the development consent order application for Dogger Bank Teesside A&B. Dogger Bank Teesside A&B comprises two 1.2 gigawatt wind farms located 165 kilometres from the UK coast at their closest point and is planned to connect to the
Forewind has started a consultation on two minor proposed changes to the development consent order application for Dogger Bank Teesside A&B. Dogger Bank Teesside A&B comprises two 1.2 gigawatt wind farms located 165 kilometres from the UK coast at their closest point and is planned to connect to the
Gardline’s Marine Wildlife Department has successfully completed the marine mammal mitigation work for the Humber Gateway Offshore Wind Farm. The wind farm will be located 8km off the East Yorkshire coast and will have 73 turbines, with a capacity of up to 219MW. Gardline worked closely with E.ON, e
The final rotor blade of the 24th wind turbine was successfully installed at the Nordsee Ost offshore wind farm over the weekend. This marks the halfway milestone of the total 48 wind turbines at RWE’s offshore wind farm, three months after the installation kicked off. “In a football match we would
RenewableUK has commented on RWE’s announcement that it does not intend to continue with the development of its 340MW Galloper offshore wind farm project in its current form. RenewableUK’s Chief Executive, Maria McCaffery, said: “Offshore wind projects stopping unnecessarily should be a matter of co