The offshore substation built for the Northwester 2 offshore wind farm has left Bladt Industries’ facility in Aalborg, Denmark, and is on its way towards the project site in Belgium. Bladt designed, built and assembled the substation with its partners Semco Maritime and ISC under a contract won in M
NKT, Energinet, and National Grid have signed the final contract documents for the supply of onshore power cables for the 1,400MW Viking Link interconnector. Under the contract valued at around EUR 90 million, NKT will deliver approximately 150 kilometres of 525kV MI high-voltage DC onshore power ca
Bladt Industries has loaded out the offshore substation destined for the Northwester 2 offshore wind farm. According to Bladt, the substation will soon leave its facility in Aalborg, Denmark, for the project site in the Belgium part of the North Sea. The 235t transformer was installed on the offshor
The BorWin3 offshore wind grid connection in the German North Sea has started transmitting power. According to Petrofac, the 900MW project has begun converting three-phase electric power generated by offshore wind farms into direct current and transmitting it 160km back to shore into the German nati
The reduction in the energy supply from the Hornsea One offshore wind farm on 9 August was caused by a lightning strike, an initial report from National Grid Electricity System Operator (NGESO) has revealed. Following the lighting strike, Hornsea One immediately de-loaded from 799MW to 62MW, the rep
Dutch contractor Visser & Smit Hanab has started installing the high-voltage cables that will connect the Windpark Fryslân offshore wind farm in the IJsselmeer to the Dutch grid. Visser & Smit Hanab will install two 25-kilometre cable sections in total to establish a connection to the high-voltage g
Dutch contractor Visser & Smit Hanab has started installing the high-voltage cables that will connect the Windpark Fryslân offshore wind farm in the IJsselmeer to the Dutch grid. Visser & Smit Hanab will install two 25-kilometre cable sections in total to establish a connection to the high-voltage g
Tekmar Energy has secured a contract with JDR Cables to provide its cable protection system (CPS) for the Formosa 1 Phase 2 offshore wind farm in Taiwan. Tekmar will supply approximately 60 of its TekLink Mechanical Latch CPS for all of the project’s inter-array and export cables, as well as 60 hang
EDS HV Group has completed cable installation, termination and testing work at the EnBW Hohe See offshore wind farm in Germany. The work was carried out as part of a contract with Zhongtian Technology Submarine Cable (ZTT) signed at the beginning of last year. Back in March 2017, ZTT won a contract
TenneT has commissioned the 900MW BorWin3 offshore grid platform in the German North Sea. BorWin3 will connect the 497MW EnBW Hohe See and the 400MW Global Tech I offshore wind farms to the German grid. It represents TenneT’s twelfth offshore wind project and takes the company’s offshore transmissio
Jan De Nul’s cable-laying vessel Willem de Vlamingh has completed the installation of the export cables on the Formosa 1 Phase 2 offshore wind farm in Taiwan. Under the EPCI contract, Jan De Nul installed 17 inter-array and three export cables at the 120MW offshore wind farm. According to the compan
Energy consultancy Xodus is to conduct a study which will investigate the integration of offshore renewables into localised energy systems around Scotland. The five-month offshore generation energy systems study, commissioned by Crown Estate Scotland, began last month. Xodus is partnering with Eleme
DEME Group’s cable laying and multipurpose vessel Living Stone has completed the installation of 85km of subsea export cable at Elia’s Modular Offshore Grid (MOG). Living Stone collected the cable at the manufacturer Hellenic Cable in Greece, transported it to the project site in Belgium and carried
DEME Group’s cable laying and multipurpose vessel Living Stone has completed the installation of 85km of subsea export cable at Elia’s Modular Offshore Grid (MOG). Living Stone collected the cable at the manufacturer Hellenic Cable in Greece, transported it to the project site in Belgium and carried